Hamilton's Road Repairs Shift into High Gear

Hamilton Township Capital Road Improvement Projects:

Road

Repair Area

Phase

Approximate Project Date (for Phase)

Crescent Avenue 

Nottingham Way to dead end

n/a

Proposed 2012 Capital Budget

Klein Avenue 

Hamilton Avenue to Liberty Street 

n/a 

Proposed 2012 Capital Budget 

Sylvan Avenue 

Perilli Drive to dead end 

n/a  

Proposed 2012 Capital Budget 

Mill Road 

South Broad Street to Church Street 

n/a  

Proposed 2012 Capital Budget 

Coleman Road  

Nottingham Way to Acres Drive 

n/a  

Proposed 2012 Capital Budget 

Parkinson Avenue 

Cedar Lane to Park Avenue 

n/a  

Proposed 2012 Capital Budget 

Whitehorse-Hamilton Square Road 

Kuser Road to Whitehorse Avenue 

n/a  

Proposed 2012 Capital Budget (partial state funding)

Acres Drive 

Nottingham Way to Compton Way 

n/a  

Proposed 2012 Capital Budget 

Ithaca Court 

Ablemarle Road to cul-de-sac 

n/a  

Proposed 2012 Capital Budget 

Arrowwood Drive 

Paxson Avenue to Bainbridge Court 

n/a  

Proposed 2012 Capital Budget 

Hampstead Road 

South Broad Street to Arena Drive 

n/a  

Proposed 2012 Capital Budget 

Reed Avenue 

Lalor Street to dead end  

n/a  

Proposed 2012 Capital Budget 

Deacon Drive 

Paxson Avenue to Youngs Road 

n/a  

Proposed 2012 Capital Budget 

Hutchinson Street

Liberty Street to Cedar Lane 

n/a  

Proposed 2012 Capital Budget 

Exton Avenue 

(Whitehorse Avenue to Hunter Avenue)

Construction

Construction - Spring 2012

Reeger Avenue     

(Lalor Street to cul-de-sac) 

Construction

Construction - Spring 2012

Park Avenue     

(Mapleshade Avenue to Cubberly Avenue) 

Under Design

Applying to NJDEP for permits; anticipated bid by Spring/Summer 2012

Hirsch Avenue 

(Cubberly Avenue to Walter Avenue) 

Under Design

Applying to NJDEP for permits; anticipated bid by Spring/Summer 2012

Mapleshade Avenue 

 

Under Design 

Applying to NJDEP for permits; anticipated bid by Spring/Summer 2012 

Woodside Avenue 

Route 156 to Iorio Drive 

Bid Out - April 2012

Construction - Spring/Summer 2012

Albert E. Bonacci Drive 

(Briarwood Drive to dead end) 

Bid Out - April 2012 

Construction - Spring/Summer 2012

Rivulet Way 

(Whitehall Road to Shady Lane) 

Pre-Construction

Construction - Spring 2012

Oaken Lane 

(Shady Lane to Rivulet Way) 

Construction

Construction - Sping 2012

Dunbar Street 

(East Franklin Street to Liberty Street) 

Construction

Construction - Spring/Summer 2012

East Franklin Street 

(Chambers Street to South Olden Avenue) 

Construction

Construction - Spring/Summer 2012

Sequola Road 

(Coldspring Road to Greentree Road) 

Bid Out - April 2012

Construction - Spring/Summer 2012

Hillhurst Avenue 

(Nottingham Way to East State Street Extension) 

Bid Out - April 2012

Construction - Spring/Summer 2012

Cardinal Road 

(Hollyknoll Drive to Greentree Road) 

Bid Out - April 2012

Construction - Spring/Summer 2012

Tyndale Road 

(Flock Road to Valley Road) 

Construction

Construction - Spring 2012 

Florister Drive 

(Paxson Avenue to Daniels Avenue) 

Construction

Construction - Spring 2012

Atlantic Avenue 

(Greenwood Avenue to Hamilton Avenue) 

Construction

Construction -  Spring 2012 

Liberty Street 

South Olden Avenue to Hamilton Avenue) 

Construction

Construction - Spring 2012 

Hamilton Township In-House Paving Project(s):

Road

Repair Area

Type of Work

Approximate Start Date

North Johnston Avenue

East State Street to Nottingham Way

Milling and paving

COMPLETED Spring 2012

Woodside Avenue

An area in between Route 156 and Route 130

Cut out and patch

COMPLETED Spring 2012

Stella Avenue

Arena Drive to cul-de-sac

Milling and paving

COMPLETED Spring 2012

Colony Drive

Quakerbridge Road to house #8

Milling and paving

COMPLETED Spring 2012

Red Cedar Drive

Limewood Drive to house #9 

Milling and paving

COMPLETED Spring 2012

Weller Avenue

South Olden Avenue to Grady Road

Milling and paving

tbd

Greentree Road

Hollynoll Drive to Sequola Road

Milling and paving

tbd

Marlow Court 

South Olden Avenue to cul-de-sac 

Milling and paving

 

tbd 

Setter Way

Sylvan Avenue to house #9

Milling and Paving 

COMPLETED Spring 2012

Galway Road

Kay Road to Rockroyal Road 

Milling and Paving 

tbd

 

Byron Avenue

South Olden Avenue to Rotunda Drive

Milling and Paving 

tbd

 

Lionel Lane

Shady Lane to Rivulet Way 

Milling and paving 

tbd 

Rockroyal Road 

Argonne Avenue 

Milling and paving

tbd

Eleanor Avenue

Johnston Avenue to cul-de-sac

 Milling and paving

tbd

Fair Lane

Bree Drive to house #4

Milling and paving 

COMPLETED Spring 2012

Intersection of Whitehorse-Hamilton Square Road and Estates Boulevard  

n/a 

Milling and paving 

tbd