Hamilton Township Capital Road Improvement Projects:
|
Road
|
Repair Area
|
Phase
|
Approximate Project Date (for Phase)
|
|
Crescent Avenue
|
Nottingham Way to dead end
|
Under Design
|
Spring 2013
|
|
Klein Avenue
|
Hamilton Avenue to Liberty Street
|
Preliminary Design
|
Spring 2013
|
|
Sylvan Avenue
|
Perilli Drive to dead end
|
Preliminary Design
|
Spring 2013
|
|
Mill Road
|
South Broad Street to Church Street
|
Preliminary Design
|
Spring 2013
|
|
Coleman Road
|
Nottingham Way to Acres Drive
|
Under Construction
|
April 2013
|
|
Parkinson Avenue
|
Cedar Lane to Park Avenue
|
Preliminaryn Design
|
Summer 2013
|
|
Acres Drive
|
Nottingham Way to Compton Way
|
Under Construction
|
April 2013
|
|
Ithaca Court
|
Ablemarle Road to cul-de-sac
|
Under Construction
|
April 2013
|
|
Arrowwood Drive
|
Paxson Avenue to Bainbridge Court
|
Preliminary Design
|
Summer 2013
|
|
Hempstead Road
|
South Broad Street to Arena Drive
|
Preliminary Design
|
Summer 2013
|
|
Reed Avenue
|
Lalor Street to dead end
|
n/a
|
COMPLETED
|
|
Deacon Drive (and part of Wolfpack Drive)
|
Paxson Avenue to Youngs Road
|
Out To Bid
|
June 2013
|
|
Hutchinson Street
|
Liberty Street to Cedar Lane
|
Preliminary Design
|
Summer 2013
|
|
Exton Avenue
|
(Whitehorse Avenue to Hunter Avenue)
|
COMPLETED
|
COMPLETED
|
|
Reeger Avenue
|
(Lalor Street to cul-de-sac)
|
COMPLETED
|
COMPLETED
|
|
Park Avenue
|
(Mapleshade Avenue to Cubberly Avenue)
|
Out To Bid
|
June 2013
|
|
Hirsch Avenue
|
(Cubberly Avenue to Walter Avenue)
|
Out To Bid
|
June 2013
|
|
Mapleshade Avenue
|
|
Out To Bid
|
June 2013
|
Hamilton Township In-House Paving Project(s):
|
Road
|
Repair Area
|
Type of Work
|
Approximate Start Date
|
| Preston Way
|
Macon Drive into Kino Boulevard |
Repaving |
COMPLETED Fall 2012 |
|
North Johnston Avenue
|
East State Street to Nottingham Way
|
Milling and paving
|
COMPLETED Spring 2012
|
|
Woodside Avenue
|
An area in between Route 156 and Route 130
|
Cut out and patch |
COMPLETED Spring 2012
|
|
Stella Avenue
|
Arena Drive to cul-de-sac
|
Milling and paving
|
COMPLETED Spring 2012
|
|
Colony Drive
|
Quakerbridge Road to house #8
|
Milling and paving
|
COMPLETED Spring 2012
|
|
Red Cedar Drive
|
Limewood Drive to house #9
|
Milling and paving
|
COMPLETED Spring 2012
|
|
Weller Avenue
|
South Olden Avenue to Grady Road
|
Milling and paving
|
COMPLETED Fall 2012
|
|
Greentree Road
|
Hollynoll Drive to Sequola Road
|
Milling and paving
|
COMPLETED Summer 2012
|
|
Marlow Court
|
South Olden Avenue to cul-de-sac
|
Milling and paving
|
Anticipated for 2013 Capital Budget due to needed curb and drainage issues
|
|
Setter Way
|
Sylvan Avenue to house #9
|
Milling and Paving
|
COMPLETED Spring 2012
|
|
Galway Road
|
Kay Road to Rockroyal Road
|
Milling and Paving
|
COMPLETED Spring 2012
|
|
Byron Avenue
|
South Olden Avenue to Rotunda Drive
|
Milling and Paving
|
COMPLETED Summer 2012
|
|
Lionel Lane
|
Shady Lane to Rivulet Way
|
Milling and paving
|
COMPLETED Summer 2012
|
|
Rockroyal Road
|
Argonne Avenue
|
Milling and paving
|
COMPLETED Spring 2012
|
|
Eleanor Avenue
|
Johnston Avenue to cul-de-sac
|
Milling and paving
|
COMPLETED Summer 2012
|
|
Fair Lane
|
Bree Drive to house #4
|
Milling and paving
|
COMPLETED Spring 2012
|
|
Intersection of Whitehorse-Hamilton Square Road and Estates Boulevard
|
n/a
|
Milling and paving
|